Day 1 Recap (November 27 2023)

Day 1 was a great success! All 4 cables were hauled across the river and 3 out of 4 cables were clamped at both ends. A start was made on the fabrication of crossbeams and suspenders, and the F value (design low point of tensioned cables) were marked on both abutments. Day 2 will consist of fully tensioning the cables using a hand winch.


    


   